Boco Rock Wind Farm is located 10km south west of Nimmitabel, and 30km north of Bombala, in NSW.  
The Windfarm consists of 67 GE 1.7MW units

 


Rex J Andrews completed the discharge, storage and delivery of all major components to the windfarm. The windfarm was discharged and stored at Eden NSW. All components were transported to Boco Rock some 1000m up from Eden.boco2boco3

boco7

 

 


The Discharge was done using the extending platform trailers, two trailers were used as they had to be reversed all the way onto the wharf (300m) as they could not turn on the wharf

boco4boco5 

Cranage at Eden Hardstand storage was completed with the Hyster RS45 "Twins", again proving their worth. The Reachstackers operated well on the hardstand surface. 


boco1Weather conditions were at times difficult, freezing diesel tanks solid.


 

 Rex J Andrews engineering division completed the design and manufacture of tower lifting adapters and spreader bars for many lifts. 

boco6

boco11

boco10


 The following adapter was designed, tested and delivered within 4 days. the bar was made up of components of less than 200kg each

boco8

boco9

Sydney
PO Box 271, Penrith NSW Australia 2751
Ph: 02 4721 7633
Fx: 02 4721 7644
Em: This email address is being protected from spambots. You need JavaScript enabled to view it.

Adelaide
PO Box 2067, Salisbury Downs SA 5108
Ph: 08 8280 5541
Fx: 08 8280 8365
Em: This email address is being protected from spambots. You need JavaScript enabled to view it.

Newcastle
16 Yilen Place, Beresfield NSW 2322
Ph: 02 4088 7002
Fx: 02 4088 7005
Em: This email address is being protected from spambots. You need JavaScript enabled to view it.